Novo Nordisk A/S
Winner
Project: NovoSeven Facility
Size: 14,000 square meters
Budget: $143 million
Key Project Participants:
- Architect, Process Design and Engineering: NNE
- Construction: MONNET (joint venture between NNE and MT Højgoerd)
- Equipment Suppliers: BBI, Millipore, Christ, Semcon, Bravida, Emerson Process Management
- Commissioning and Validation Consultant: NNE
Timeline:
- 18 months from basic design approval to handover
Alkermes, Inc.
Finalist
Project: Brickyard Square Manufacturing Facility
Size: 90,000 square feet available; 45,000 square feet used initially
Budget: $40 million
Key Project Participants:
- Architect, Engineer, and Construction Manager: Parsons Corporation
- Equipment Suppliers: Niro, MG America, Electrol Specialties Company, Superior Controls
- Installation Contractors: Joseph P. McCabe, TJ McCartney, Dynamic Systems, Berkshire Bridge & Iron, Coghlin Electric, Beacon Piping, Worcester Air, Andover Controls, Valante Mechanical
- Validation: cGMP Validation
Timeline:
- Detailed Design Start: September 2001
- Construction Start: January 2002
- Construction Completion: April 2003
- Validation Completion: March 2004
Apotex, Inc.
Finalist
Project: Etobicoke Expansion Project
Size: 428,500 square feet
Budget: $238 million
Key Project Participants:
- Architect: Whitney Bailey Associates
- Mechanical and Electrical Design: AMEC Americas Ltd.
- Construction Support: Vanbots Construction Corporation
- Equipment Suppliers: FMC Technologies, FKI Logistex, Grantek Control Systems, ThermoSystems, NJM/CLI Packaging Systems, Korsch America, IMA North America, Girton Manufacturing, Gerteis Maschinen + Processengineering AG
Timeline:
- Construction: January 2002 - December 2003
- Production Start-Up: June 2004
Kowa Company Ltd.
Finalist
Project: Kowa Nagoya Project
Size: 8,520 square meters
Budget: $38.8 million
Key Project Participants:
- Architect: Shimizu Corporation
- Process and Engineering Design: Hitachi Plant Engineering and Construction, Ltd., ELVECO
- Equipment Suppliers: Toyota Industries Corporation, Murata Works Ltd.
Timeline:
- Construction to Delivery: August 2002 - July 2003
Lundbeck Pharmaceuticals Ltd.
Finalist
Project: Lundbeck Pharmaceuticals API Manufacturing Facility - P7
Size: 6,000 square meters
Budget: 50 million
Key Project Participants:
- Engineering, Design, Procurement, Construction, and Validation: Foster Wheeler
- SMB and Filter Driers: Novasep
- Financial Support: Northcroft
- Civils Contract: Interserve
- Materials and Labor Subcontracts: Caxios, SEC, Cordell
Timeline:
- Construction Begins: April 2000
- PQ Completion: May 2003
- FDA Inspection: June 2003